16 July 2007

Its Time To Gyprock

Now he may look professional on those stilts but that is our son Tim who came home for a week to help me put the gyprock in the basement cinema room. We were certainly glad that we had chosen to load all the necessary sheets down in basement before we poured the top slab.

05 July 2007

19 Months Later and We Are At "Lock Up"



The outside of house is nearly finished. Just need to wait for render to dry prior to painting. Also need to tile the verandah prior to getting the bullnose vernadah erected. The back still has heaps to do. Have to put all the deck down as well as pavers and lawn. I had to build the pergola so that the plumber could install the box gutter. Can't wait to relax out back rather than house building every waking moment


14 April 2007

The Bricky Is Back


Its April '07 and we got the roof on. I have also installed all the cedar window frames. (That was after I had put 2 coats of sealer on all of them). The window slides are currently being double glazed. There is also a number of windows that I am making leadlight for. The bricky is currently laying the limestone quoins and side walls. The front of the house will be sandstone.

04 December 2006

Erecting the Framework



At the end of August 2006 we finally got to build with some timber. So sick of concrete and steel. Finally got to get an impression of what the house will look like. We decided to use the termite treated timber just for added insurance. Still been very wet while we have been doing this frame work. Now looking forward to getting a roof and keeping dry.

18 June 2006

Building The Basement




Its May 2006 and it has been alot of hard work to get to this stage. It was a huge job digging out the hole for the basement and then erecting all the retaining walls. We are now building up the block walls. The exterior walls are 200mm core filled concrete blocks. On the outside of this wall there is 100mm limestone wall. Horizontal rebar reinforcing had to be laid every 400mm and the vertical reinforcing every 200mm. This stage of building is in the middle of winter so subsequently I had to pump a fair amount of water out of the basement on a regular basis.

Once all the masonry work was done I had to "tank" the walls with a bitumin sealer. This was then covered with a plastic protector board and then finally all that was covered with a plastic membrane. Ag drains were put around the exterior walls and then backfilled with gravel. Once the steel I beams were in it was time to lay the bondek & steel reinforcing. Finally ready to pour the main house slab.

24 January 2006

The start of our new house

At last - we have started building our new house. There has been lengthy delays getting to this stage. Getting final council approval took a lot longer than normal. Whilst the main living area is going to be smaller than our current house we decided to include an underground cimema / pool room. The underground room is 5.5metres x 14metres. The decision to do this room has been a major factor in the time taken to build. (Plus we will be doing most of the work ourselves on our days off!!)